Capacity demand template
Copy these tables for each Capacity Operations (CapOps) demand submission. Replace the prompts, give the submission a stable identifier, and preserve versions when dates or quantities change. Use unknown with an investigation owner rather than leaving a decision-critical field silently blank. Link confidential evidence in an approved system; do not paste it into a public copy.
Business context and ownership
| Field |
Entry |
| Demand identifier and version |
Stable identifier, version, and change date |
| Workload and profile reference |
Service name and link to owned workload profile |
| Business owner and technical contact |
Names, authority, and deputies |
| Business outcome and demand driver |
Milestone plus transactions, users, data, or other sizing driver |
| Required date and critical period |
Date, time zone, business window, and consequence of delay |
| Priority and business consequence |
Locally defined criticality and impact of reduced or delayed service |
| Demand horizon |
Near, medium, or long; record the locally defined date range |
| Permitted flexibility |
Approved changes to quantity, schedule, family, service pattern, or location |
| Non-negotiable constraints |
Location, regulatory, performance, dependency, or operational restrictions |
| Previous submission superseded |
Reference and explanation of the change; avoid duplicate demand |
Technical demand slices
Repeat a row for each compatible service-family-location-time slice. Do not combine different units or assume equal unit counts imply equivalent performance.
| Slice identifier |
Scenario |
Service and family |
Quantity and unit |
Location and zone constraints |
Start, ramp, and duration |
Total or incremental |
Sizing evidence |
| Enter slice |
Normal, peak, recovery, or named combined scenario |
Exact technical shape |
Number or range with unit |
Primary and permitted scope |
Dates and growth steps |
State relationship to baseline |
Test or model reference and observed date |
Assumptions and dependencies
| Item |
Assumption or requirement |
Evidence and date |
Overlap or dependency |
Owner and validation action |
| Baseline and business translation |
Usage baseline and conversion model |
Reference, period, and limitations |
Resources included or excluded |
Named owner and next check |
| Peak |
Uplift and duration; total or incremental |
Test or business-plan reference |
Can it overlap recovery or migration? |
Named owner |
| Recovery |
Restoration phases and separate destination profile |
Recovery-profile reference |
Concurrent services and destination resident load |
Continuity and dependency owners |
| Retirement or migration |
Units added, retained temporarily, or removed |
Approved retirement or wave plan |
Conditions before subtracting demand |
Named owner and deadline |
| Uncertainty |
Scenario range and confidence rationale |
Supporting observation |
Factors that would invalidate sizing |
Evidence owner |
| Alternative |
Family, location, service pattern, schedule, or reduced demand |
Validation status and cost reference |
Prerequisites and implementation lead time |
Technical and business authorities |
Supply-posture evidence
| Evidence type |
Scope and quantity |
Reference and observed date |
Conditions or exclusions |
Freshness rule and next check |
| Quota permission |
Applicable administrative scope |
Limit and request outcome |
Permission only; not physical capacity |
Date or event trigger |
| Financial obligation |
Eligible economic scope |
Terms and approval reference |
Do not infer deployable entitlement |
Commercial review |
| Capacity mechanism |
Exact eligible family, location, dates, and quantity |
Current terms and mechanism reference |
Documented conditions and remaining prerequisites |
Technical and commercial refresh |
| Allocation and deployment |
Assigned consumer and observed request scope |
Ledger and deployment result |
Observation applies to its tested time and scope |
Operational trigger |
Decision handoff
| Field |
Entry |
| Material gap and risk reference |
What remains unestablished and its business consequence |
| Recommended option |
Rationale, alternatives, and residual risk |
| Last responsible decision deadline |
Option-specific date and lead-time calculation |
| Decision authority and requested action |
Who may approve, change, hold, or accept the stated risk |
| Implementation owner and due date |
Who acts after approval |
| Acceptance evidence |
What must be observed before the action or risk closes |
| Review trigger and next review |
Demand change, stale evidence, deadline, or scheduled review |
| Business and technical validation |
Names, dates, scope, and unresolved disagreements |
A forecast, quota, financial discount, or service listing is not a capacity guarantee. If using “secured,” state the mechanism, exact conditions, and residual limitations.