Monthly review template

Copy these tables for each monthly Capacity Operations (CapOps) review. Link the maintained records rather than duplicating their full contents. Replace prompts with evidence and decisions. Remove unused example rows, not required checks. Escalate urgent items before the meeting if their decision deadlines cannot wait.

Review context

Field Entry
Review identifier, date, and observation period Stable reference, time zone, and evidence cut-off
Scope and forecast versions Workloads, locations, scenarios, and versions considered
Facilitator and record owner Practice steward and publication owner
Decision authorities and deputies Required business, technical, commercial, release, or continuity authorities
Evidence freshness and gaps Local rule, stale sources, unknowns, and assigned investigations
Previous review and urgent decisions Links and changes already decided through incident or deadline escalation

Decisions required and outcomes

Decision identifier and question Business consequence and scope Evidence and freshness Options and recommendation Authority Last responsible decision deadline Outcome and conditions
Enter decision Workload, scenario, service, family, quantity, location, date References and material limitations Feasible options and trade-offs Named approver Option-specific date Approve, change, hold, exception, or escalate; link record

Demand changes

Workload and demand version Previous scenario demand New scenario demand Business reason Effective window and ramp Retirement or overlap assumptions Owner validation
Profile reference Quantity, unit, family, location, period Same dimensions or explicit change Launch, growth, peak, recovery, or retirement Dates and duration Concurrent demand and dependencies Name, date, and outstanding gaps

Risks, commitments, and recovery

Record reference Material change or gap Business exposure Evidence and scope Choice required Authority and deadline Resulting action
Risk record Changed event, assumption, or mitigation Milestone and residual risk Source and observed date Mitigate, investigate, or accept Named authority and date Owner, due date, closure test
Commitment record Acquired, unassigned, idle, expiring, or incompatible Obligation and consumer effect Terms, assignment, consumption Retain, assign, reassign, amend, renew, or release Commercial or technical authority Owner and verification
Recovery profile Concurrent demand or validation gap Affected business functions Scenario, test scale, exclusions, date Protect, sequence, test, change objective, or accept Continuity or business authority Owner and verification
Exception record New, changed, or expiring deviation Residual exposure Conditions and compensating controls Close, replace, or seek new approval Risk authority and expiry Action and revisit trigger

Follow-through and incident learning

Action or finding Previous decision Executor Due date Evidence required for closure Observed result Reopen or escalation trigger
Specific action Linked authority and conditions Named owner Date Test or verified record change Pending, partial, failed, or verified; reference Changed assumption, failed test, or missed deadline

Operational and executive reporting

Audience Content to publish Evidence and decision links Owner and publication date
Operational teams Scoped gaps, allocation changes, errors, freshness issues, obligations, and actions with deadlines Detailed records and acceptance tests Named owner
Executives and portfolio authorities Milestones exposed, conflicting priorities, continuity gaps, residual risks, and funding or sequencing decisions Short decision briefs with traceable supporting evidence Named owner

Any scorecard measure needs an organization-defined target, explicit scope, denominator where applicable, and data freshness. A “secured” total without mechanism conditions and demand dimensions must not be used as readiness proof.